Section 2.9 Alternatives (1001.9 Exhibit 9: Alternatives)
(pp. 42-51)
1. One aspect of “alternative
location” (16 NYCRR Part 1001.9) that should be evaluated is one or more
alternative layouts with a reduced project footprint within the project area.
Staff recommends that the
application address alternative facility arrangements, including:
(a)
Alternative
arrangements for the various project sizes that may result from use of
different size turbines, (e.g., indicating which of the 124 turbine locations
would be used for the 285 MW project using 95 turbines rated at 3.0 MW);
(b)
An
alternative arrangement that avoids locating wind turbines in exclusion zones
specifically identified in the Cape Vincent Zoning Regulations;
(c)
An
alternative arrangement that would not require Siting Board approval (e.g., a
24.9MW project to be reviewed by the Town of Cape Vincent per applicable
regulations);
(d)
Alternative
location for the Operations and Maintenance building, that would locate that
facility near the collection substation;
(e)
An alternative underground arrangement for the
proposed 115 kV transmission and
switchyard-to-substation interconnection line, including associated cost
information; and,
(f)
An alternative underground arrangement for the
proposed 115 kV transmission interconnection line at the crossing of the
Chaumont River corridor.