December
20, 2012
Honorable
Jeffrey C. Cohen
Acting
Secretary, NYS Board of Electric Power Generation Siting and Environment
3 Empire
State Plaza
Albany,
NY 12223-1350
Re: Case12-F-0410 Cape Vincent Wind Power
Dear
Acting Secretary Cohen:
Regarding
the revised Public Involvement Program (PIP) dated Nov. 12, 2012 from BP, there
are several areas where the DPS made specific recommendations as to what actions
were necessary to make the original PIP plan adequate. The following requests
from the DPS were not met in BP's revised PIP, nor did BP provide a written
explanation as to why it decided not to incorporate DPS's recommendations.
We wish to make clear, for the record that BP’s
revised PIP is substantially lacking.
From
the DPS letter Oct. 17, 2012 “Pursuant to 16
NYCRR 1000.4 (e), Cape Vincent Wind Power, LLC shall within 30 days consider the
measures recommended by DPS and, in a final written Public Involvement Program plan
filed with the Secretary, shall as to each specific measure either revise the
Public Involvement
Program plan to incorporate the DPS recommendation, or provide a written explanation
as to why it decided not to incorporate the recommendations.”
And
“The PIP should identify a proposed Study Area, and identify any
additional stakeholders or
stakeholder groups that are within that broader area.
Representatives and residents of adjacent
municipalities (e.g., Town of Clayton; Wolfe Island, Ontario)
should be considered as potential
stakeholders based on regional scale impacts of the proposed
large-scale wind energy project,
and potential cumulative impacts with existing or proposed wind
energy facilities in those
jurisdictions.”
However,
Wolfe Island, an existing project, and Clayton, a proposed project, were not
included in BP's revised PIP.
The DPS
also wrote:
"In addition, we would appreciate it if you could provide
DPS with some basic project
information including (a) a map showing the project area
including the turbine array limits, and
the location of electric lines, substations, switchyard and
interconnection points; and (b) a
description of the changes resulting in the consolidated project
including the number and size of
turbines, their location, and the project boundary."
BP
ignored this recommendation by DPS in their revised PIP and did not change a
single feature of their original map "Exhibit 1- Map of Cape Vincent Wind
Farm." BP's map lacks boundaries of the project, setbacks from property
lines, location of turbines, a legend of host landowners and adjacent
landowners. Locations of electric lines, substations, switchyards, and
interconnection points are vague and indeterminable.
In BP’s
revised PIP on page 4 there is a chart which describes setbacks distances from
non-participating landowners, yet their map does not delineate which properties
are non- participating making interpretation of setback distances impossible.
The DPS
further writes:
“3. The Plan should provide a preliminary specific (non-generic)
identification of: (i) host
landowners; and (ii) adjacent landowners;….”
Again,
no such information is included and the recommendations of DPS were ignored.
BP
writes in their revised PIP “...has developed
a list of stakeholders using the following criteria (a preliminary specific
list of stakeholders is
attached as Exhibit 3):”
Exhibit
3, however, lacks lists of specific host landowners and adjacent property
owners. The Lyme Planning Board is not entirely represented and Clayton and
Wolfe Island are not included. In this instance BP has failed to include what
they said they would include!
DPS
writes:
“1. The Public Involvement Program plan (Plan) should identify:
(c) the location of reasonable
alternative sites,…..” BP’s revised PIP has no
alternate facility sites proposed, nor did BP provide an explanation as to why
they ignored
DPS's recommendations.
DPS
writes:
“9. The Plan should include a provision that the Applicant will
prepare a monthly spread sheet style tracking report identifying public
involvement program activities conducted by the
Applicant, summaries of feedback received in such activities,
and summaries describing any
actions taken by the Applicant in response to such feedback.”
BP
officially began their PIP Sept. 17. To date their website has neither
summaries of feedback from the public nor summaries of actions taken by BP in
response to feedback. It has been two months and their web-page is blank along
with their response to DPS.
DPS
writes:
“Identification of goals and methods for specific
consultations...d) provide a methodology to
measure the
success of the outreach. “
BP
responds in their revised PIP:
"...consultation will be deemed successful if information
relevant to affected stakeholder or
agency was provided to affected agency or stakeholder,..” In addition to information requested in previous letters to the
PSC and BP, the Town of Cape Vincent has requested:
An accurate map with specifics details
lists of host landowners and adjacent landowners
accurate and definitive size of project -
200-285 MW has a 42% variation
accurate numbers for productivity- not
exaggerated by at least 3 times
acknowledgement that significant adverse
environmental, social, financial, and cultural impacts exist
respect for our Town Comprehensive Plan and
our Local Zoning Laws.
In spite of these requests, BP chose to ignore
the Town's requests in much the same manner that they have ignored DPS
recommendations for improving their PIP.
There
has to be some recognition in the Article 10 process between an applicant's
rhetoric and their compliance with the law, rules and the recommendations of
the DPS. In BP's Article 10 case they obviously talk better than they walk.
Although we view the loss of home rule to be unfair to the interests of our
community, we felt the rules that were promulgated by DPS attempted to balance
the interests of all the players, us included. However, if BP continues to be
unresponsive to these rules, as they have been with their PIP, then we foresee
a continued adulteration of the Article 10 process. Governor Cuomo, during the
signing of the NY Power Act 2011, stated that “the process will be fair,” and
we hope and expect that the Siting Board will uphold the expectation of the
governor.
Respectfully
yours,
Urban
Hirschey – Town Supervisor
Brooks
Bradgon – Deputy Supervisor
John
Byrne – Town Council
Clifford
Schneider – Town Council
Michelle
Oswald – Town Council
Richard
Macsherry – Planning Board Chairman
Robert S.
Brown – Planning Board
Cyril
Cullen – Planning Board
Paul
Docteur – Planning Board
Hester Chase – Zoning Board
3 comments:
Bam! Sock! Pow!
But the Big Wind Monolith still stands.
More David, more, more, more...
THANK YOU VERY MUCH. The board's response clearly outlines many aspects that BP has chosen to ignore. How might this play out now that the psc is aware of BP's blunders to adhere to the Article Ten process? Please watch the link to a video. If you can't watch it all, then jump to about 6:00 to about 8:42 on the counter.
http://www.youtube.com/watch?v=HowKoNmODNY
The more straightforward and specific the questions you ask of BP the less likely it is that there will be any answers.
These guys are flim-flam speculators in the tax credit swap market. They aren't going to be bothered giving any details o the little people unless it is first determined by them that they can get this thing done and qualify for some tax credits.
It could be Cape Vincent or it could be Timbuktu; doesn't matter to them. Some dead birds and plummeting home values don't matter to them either.
Post a Comment