Friday, December 21, 2012

Cape Vincent Comments to Public Service Commission

RE: BP ~ PIP


  
December 20, 2012
Honorable Jeffrey C. Cohen
Acting Secretary, NYS Board of Electric Power Generation Siting and Environment
3 Empire State Plaza
Albany, NY 12223-1350


Re: Case12-F-0410 Cape Vincent Wind Power

Dear Acting Secretary Cohen:
Regarding the revised Public Involvement Program (PIP) dated Nov. 12, 2012 from BP, there are several areas where the DPS made specific recommendations as to what actions were necessary to make the original PIP plan adequate. The following requests from the DPS were not met in BP's revised PIP, nor did BP provide a written explanation as to why it decided not to incorporate DPS's recommendations.
 We wish to make clear, for the record that BP’s revised PIP is substantially lacking.

From the DPS letter Oct. 17, 2012 “Pursuant to 16 NYCRR 1000.4 (e), Cape Vincent Wind Power, LLC shall within 30 days consider the measures recommended by DPS and, in a final written Public Involvement Program plan filed with the Secretary, shall as to each specific measure either revise the Public Involvement Program plan to incorporate the DPS recommendation, or provide a written explanation as to why it decided not to incorporate the recommendations.”

And

The PIP should identify a proposed Study Area, and identify any additional stakeholders or
stakeholder groups that are within that broader area. Representatives and residents of adjacent
municipalities (e.g., Town of Clayton; Wolfe Island, Ontario) should be considered as potential
stakeholders based on regional scale impacts of the proposed large-scale wind energy project,
and potential cumulative impacts with existing or proposed wind energy facilities in those
jurisdictions.”

However, Wolfe Island, an existing project, and Clayton, a proposed project, were not included in BP's revised PIP.

The DPS also wrote:

"In addition, we would appreciate it if you could provide DPS with some basic project
information including (a) a map showing the project area including the turbine array limits, and
the location of electric lines, substations, switchyard and interconnection points; and (b) a
description of the changes resulting in the consolidated project including the number and size of
turbines, their location, and the project boundary."

BP ignored this recommendation by DPS in their revised PIP and did not change a single feature of their original map "Exhibit 1- Map of Cape Vincent Wind Farm." BP's map lacks boundaries of the project, setbacks from property lines, location of turbines, a legend of host landowners and adjacent landowners. Locations of electric lines, substations, switchyards, and interconnection points are vague and indeterminable.
In BP’s revised PIP on page 4 there is a chart which describes setbacks distances from non-participating landowners, yet their map does not delineate which properties are non- participating making interpretation of setback distances impossible.

The DPS further writes:
3. The Plan should provide a preliminary specific (non-generic) identification of: (i) host
landowners; and (ii) adjacent landowners;….”

Again, no such information is included and the recommendations of DPS were ignored.

BP writes in their revised PIP “...has developed a list of stakeholders using the following criteria (a preliminary specific list of stakeholders is attached as Exhibit 3):”

Exhibit 3, however, lacks lists of specific host landowners and adjacent property owners. The Lyme Planning Board is not entirely represented and Clayton and Wolfe Island are not included. In this instance BP has failed to include what they said they would include!

DPS writes:

1. The Public Involvement Program plan (Plan) should identify: (c) the location of reasonable
alternative sites,…..” BP’s revised PIP has no alternate facility sites proposed, nor did BP provide an explanation as to why they ignored DPS's recommendations.

DPS writes:

9. The Plan should include a provision that the Applicant will prepare a monthly spread sheet style tracking report identifying public involvement program activities conducted by the
Applicant, summaries of feedback received in such activities, and summaries describing any
actions taken by the Applicant in response to such feedback.”

BP officially began their PIP Sept. 17. To date their website has neither summaries of feedback from the public nor summaries of actions taken by BP in response to feedback. It has been two months and their web-page is blank along with their response to DPS.

DPS writes:

Identification of goals and methods for specific consultations...d) provide a methodology to
measure the success of the outreach. “
BP responds in their revised PIP:

"...consultation will be deemed successful if information relevant to affected stakeholder or
agency was provided to affected agency or stakeholder,..” In addition to information requested in previous letters to the PSC and BP, the Town of Cape Vincent has requested:
An accurate map with specifics details
lists of host landowners and adjacent landowners
accurate and definitive size of project - 200-285 MW has a 42% variation
accurate numbers for productivity- not exaggerated by at least 3 times
acknowledgement that significant adverse environmental, social, financial, and cultural impacts exist

respect for our Town Comprehensive Plan and our Local Zoning Laws.

 In spite of these requests, BP chose to ignore the Town's requests in much the same manner that they have ignored DPS recommendations for improving their PIP.

There has to be some recognition in the Article 10 process between an applicant's rhetoric and their compliance with the law, rules and the recommendations of the DPS. In BP's Article 10 case they obviously talk better than they walk. Although we view the loss of home rule to be unfair to the interests of our community, we felt the rules that were promulgated by DPS attempted to balance the interests of all the players, us included. However, if BP continues to be unresponsive to these rules, as they have been with their PIP, then we foresee a continued adulteration of the Article 10 process. Governor Cuomo, during the signing of the NY Power Act 2011, stated that “the process will be fair,” and we hope and expect that the Siting Board will uphold the expectation of the governor.


Respectfully yours,

Urban Hirschey – Town Supervisor

Brooks Bradgon – Deputy Supervisor

John Byrne – Town Council

Clifford Schneider – Town Council

Michelle Oswald – Town Council

Richard Macsherry – Planning Board Chairman

Robert S. Brown – Planning Board

Cyril Cullen – Planning Board

Paul Docteur – Planning Board

Hester Chase – Zoning Board

3 comments:

Anonymous said...

Bam! Sock! Pow!

But the Big Wind Monolith still stands.

More David, more, more, more...

Anonymous said...

THANK YOU VERY MUCH. The board's response clearly outlines many aspects that BP has chosen to ignore. How might this play out now that the psc is aware of BP's blunders to adhere to the Article Ten process? Please watch the link to a video. If you can't watch it all, then jump to about 6:00 to about 8:42 on the counter.

http://www.youtube.com/watch?v=HowKoNmODNY

Anonymous said...

The more straightforward and specific the questions you ask of BP the less likely it is that there will be any answers.

These guys are flim-flam speculators in the tax credit swap market. They aren't going to be bothered giving any details o the little people unless it is first determined by them that they can get this thing done and qualify for some tax credits.

It could be Cape Vincent or it could be Timbuktu; doesn't matter to them. Some dead birds and plummeting home values don't matter to them either.