Saturday, March 2, 2013

State justice dismisses suit by wind power developer

 A State Supreme Court justice has dismissed a lawsuit brought against the Town of Allegany Planning Board by a wind power development company.

In December, Everpower sued both the Town of Allegany and the Allegany Planning Board, claiming the board's request for a supplemental review of noise impacts, in light of the wind power company's request to use larger turbine blades, was arbitrary.

[The Buffalo News]

2 comments:

Anonymous said...

The judge cited "Everpower’s conduct as willfully obstinate."

If ever a developer was "willfully obstinate" it is BP Wind.

The motto of BP Wind should be a phrase that the author of this blog would be too polite to print.

Anonymous said...

Bee Pee's chart was a joke. Notice on it that Bee Pee is not getting away with meeting with all groups alone and letting secret deals go down without the town and village knowing. Mr. H. is doing a good job making sure of that.