Thursday, August 8, 2013

Wind farm litigants square off

Opening arguments were made Monday in a lawsuit over $56 million of contract work allegedly not paid for as the Mehoopany Wind Farm was completed in 2012.
Attorney Doug Kilday, representing RES Americas – the company responsible for getting 88 windmills in the ground – told Wyoming County President Judge Russell Shurtleff that his firm worked to get the wind farm completed by Dec. 31, 2013, when federal tax credits were due to expire.
RES Americas is suing Mehoopany Wind Energy LLC which owns the property on which the farm was built and its partner, BP Wind Energy.Continue... [WC Examiner]